LAMBERT-ST. LOUIS INTERNATIONAL – TAXIWAY REHABILITATION PROGRAM

KWAME led a joint venture team – along with Howard R. Green Company – served as Construction Manager for a $27 million rehabilitation of a taxiway, relocation of a roadway and construction of perimeter fencing at Lambert-St. Louis International Airport.

The American Concrete Pavement Association recognized the KWAME/Green Joint Venture for their work on the reconstruction of taxiway F, L & S at Lambert-St. Louis International Airport. The project was rated the “best commercial service and military airport concrete paving project completed in Missouri in 2007.”

Client Contact

Richard Bradley, PE
President, Board of Public Service
City of Saint Louis
1200 Market Street, Room 301
St. Louis, MO 63101

Construction Cost

$27 Million

Completion Date

2007